Site plan requirements and actions 22
•
Ensure that the site safety and security programs are properly administered.
•
Interface directly with the HP installation project manager to ensure clear lines of communication during
the installation and commissioning processes.
the installation and commissioning processes.
Site planning
A comprehensive site plan assists with the site design (MEP) and ensures the best possible HP POD 20c
installation process. When creating a site plan, consider the following information:
installation process. When creating a site plan, consider the following information:
•
HP POD 20c site requirements detailed in this document
•
HP POD 20c site preparation drawing package
•
HP POD 20c readiness checklist ("
" on page
•
The HP team can assist you by answering questions and help to guiding you throughout the process.
HP POD 20c installation
HP POD 20c installation includes the following:
•
•
•
•
Installation equipment staging
Staging for the following items must be identified and considered:
•
Truck and component staging
•
Installation equipment staging
•
Site traffic
•
Regulatory or local permits
HP POD 20c lifting layout
When preparing a site plan, identify where to place the HP POD 20c and the equipment that is used for
assembly. The following figure shows an HP POD 20c assembly site and includes:
•
HP POD 20c location
•
Crane location