HP Performance Optimized Data Center (POD) 40cp 사용자 설명서
Optional components 45
Each external panel is secured through key lock hardware.
The following locations have been prewired for your own security upgrades.
The following locations have been prewired for your own security upgrades.
Callout Description
1
Prewired junction box locations
2
Card reader locations
3
Internal camera locations
4
External camera locations
Transformers and switchboards
HP offers several transformers and switchboards to supply your power needs.
On-site connections include:
On-site connections include:
•
From your main facility power to the primary side of the transformer
•
From the transformer to the switchboard
•
From the feeder breaker lugs within the switchboard assembly to the HP POD
The standard cables should allow for placing the transformer and switchboard approximately 3.0 m (10
ft) away from the HP POD. Installation costs assume that connections are within the 3.0 m (10 ft)
recommendation. If you place the transformer and switchboard more than 3.0 m (10 ft) away from the HP
POD, additional planning and costs are involved.
POD, additional planning and costs are involved.
Water distribution kit
HP recommends using the optional water distribution kit to provide water to your HP POD. For more
information about the kit, see Water distribution kit components ("
NOTE:
The water distribution kit pipes are flushed prior to shipment.
The water distribution kit is enclosed within a 10 ft ISO container that includes internal lighting and
heating. The heater comes equipped with a programmable thermostat that you can set to run as needed
to ensure the water temperature inside does not drop below freezing.