Installation 
New Actuators, Remove Pre-load 
 
GCA, GBB, GIB 
GMA, GEB 
EA1
179R1
 
Figure 3.  Determine Actuator Model and Orientation. 
NOTE:  For in-service actuators, skip Removing Pre-
load. For new actuators, remove the factory-
installed 5° pre-load. 
Removing Preload 
Before the External Auxiliary Switch can be installed on 
a new, out-of-the-box actuator, you must remove the 
factory-installed preload. 
New Non-Spring Return Actuators 
1.  Insert shaft adapter at position A (See Figure 4)
2.  Press the manual override button and move the 
shaft adapter counterclockwise until actuator 
reaches the internal stop (actuator will not move 
past this point). 
3.  Remove the shaft adapter and manually reinstall it 
against the external end stop at position B (See 
Figure 4). 
4.  Proceed with EAS installation. 
90
90
EA1190R1
PUSH
 
Figure 4.   
Insert Shaft Adapter at Position A. 
New Spring Return Actuators 
1.  Without the shaft adapter installed, using the hex 
wrench, wind the manual override one full 
revolution and release the wrench (See Figure 5). 
The actuator will return to the 0° position and the 
preload is now removed. 
 
EA1192R1
1-Turn
Manual
Override
Figure 5. 
2.  Manually install the shaft adapter against the 
external stop on the left end of the actuator. (See 
position B in Figure 4.) 
Removing Factory Pre-load from New SR Actuator. 
Preparing the Actuator Shaft Adapter 
1.  Remove the position indicator from an in-service 
actuator. 
2.  Determine the appropriate position adapter ring 
3.  Align and snap the three open notches on the edge 
of the EAS position adapter ring in place over the 
three raised stubs on the actuator shaft adapter.  
(See Figure 6)
EA1
177R1
 
NOTE:  
GCA/GBB/GIB 
models use the 
larger ring. 
GMA/GEB models 
use smaller ring.
See Figure 1. 
Figure 6.  Attaching the EAS Position Adapter Ring. 