12. CHECK AFTER INSTALLATION AND TEST RUN
                
12.1 Check After Installation
Check the items listed in below table after installation of air conditioner.
12.2  Test Operation
12.2.1 Before Test Operation
    •  Do not switch on power before installation is finished completely
    •  Electric wiring must be connected correctly and securely.
    •  Cut-off valves of the connection pipes should be opened.
    •  All the impurities such as scraps and thrums must be cleared from the unit.
12.2.2 Test Operation Method
    •  Switch on power, press "ON / OFF" button on the wireless remote controller to start the 
operation. 
     
    •  Press MODE button, to select the “COOL”, “FAN” mode to check whether the operation is 
normal or not. 
      
Items to be checked
Possible malfunction
• Has it been fixed firmly?
• The unit may drop, shake or emit noise.
• Have you done the refrigerant leakage 
test?
• It may cause insufficient of cooling 
  capacity.
• Is heat insulation sufficient?
• It may cause condensation and dripping
• Is water drainage well?
• It may cause condensation and dripping.
• Is the voltage in accordance with the rated 
  voltage marked on the nameplate?
• It may cause electric malfunction or 
  damage the part.
• Is the electric wiring and piping connection 
  installed correctly and securely?
• It may cause electric malfunction or 
  damage the part
• Has the unit been connected to a secure 
  earth connection?
• It may cause electrical leakage.
• Is the power cord specified?
• It may cause electric malfunction or 
  damage the part
• Is the inlet and outlet been covered?
• It may cause of insufficient cooling 
  capacity.
• Has the length of connection pipes and 
  refrigerant capacity been recorded?
• The refrigerant capacity is not accurate.
Installation Service