II-C. Leveling and Grouting of 
Baseplate Initial Alignment Check
1.  Put  the  unit  in  place  on  wedges  located  at  four  points  as 
shown in Fig. 2. Some long installations may require additional 
wedges near center of bedplate.
2.  Adjust  wedges  to  level  unit  (approximately),  placing  unit 
between 3⁄4” and 11⁄2” above foundation. Level or plumb suction 
and  discharge  flanges.  Then,  bring  the  coupling  halves  into 
reasonable alignment by adjusting the wedges as needed.
3. Make sure that the baseplate is not distorted and that final 
accurate coupling alignment can be established within the limits 
of movement of motor and by shimming motor if necessary.
4.  Tighten  foundation  bolts  finger  tight.  Build  dam  around 
foundation and pour grout. Fill to level of grout hole making 
sure that the areas under the pump and motor feet are filled 
solid. Allow grout to harden at least 48 hours before further 
tightening foundation bolts. Tighten pump hold down bolts.
II-D. Piping Practices
Guidelines  for  piping  are  given  in  the  “Hydraulic  Institute 
Standards” and should be reviewed prior to pump installation. 
All piping should be supported independently of, and line up 
naturally  with,  the  pump  flanges.  NEVER  DRAW  PIPING 
INTO  PLACE  BY  USE  OF  FORCE  AT  THE  FLANGED 
CONNECTIONS OF THE PUMP. 
Both suction and discharge piping should be as short and direct 
as possible to minimize friction losses. Foundation, pump and 
driver hold–down bolts should be tightened prior to connecting 
suction or discharge piping to the pump.
On  units  handling  corrosives,  the  piping  can  be  arranged  to 
allow  flushing  of  the  pump  prior  to  opening  of  the  unit  for 
servicing. After connecting suction and discharge piping to the 
pump, rotate pump by hand to be sure that there is no binding.
II-E. Alignment—Preliminary
Alignment of the pump and driver is of extreme importance 
for  trouble–free  mechanical  operation.  Alignment  should  be 
obtained by adding or removing shims from under the motor 
feet. The pump bearing frame foot should never be adjusted 
to obtain alignment. The proper shimming is installed under 
the  bearing  frame  foot  at  the  factory  on  units  shipped  with 
bedplates. Changing the pump casing or bearing frame in the 
field will require a reshimming of the frame foot. The proper 
number of shims is installed when the pump shaft is level and 
parallel to the bedplate surface. Proper shimming is achieved 
by loosening frame foot and tightening casing foot. This should 
create a gap between the frame foot and bedplate between 0 
and  .040  inches  (1mm).  This  must  be  filled  with  shims  and 
the frame foot retightened. If this procedure is not followed, 
mechanical problems can result. The final alignment is done 
after the unit has been run under actual operating conditions. 
The following are suggested steps for aligning the unit, prior to 
initial startup.
1.  Parallel  Alignment:  The  unit  is  in  parallel  misalignment 
when  the  shaft  axes  are  parallel,  but  not  concentric.  During 
initial alignment, vertical parallel alignment may be different, 
due  to  thermal  expansion  of  the  unit  at  actual  operating 
conditions. The following is a suggested cold setting for motor 
driven units:
 
Pumpage
 
Temperature 
 
Above Ambient 
Set Motor Shaft 
 
Ambient 
.002–.004” low (.05–.10 mm)
 
100° F.  
.000–.002” high (.00–.05 mm)
 
200° F. 
.004–.006” high (.10–.15 mm)
 
300° F. 
.008–.010” high (.20–.25 mm)
 
400° F. 
.012–.014” high (.30–.35 mm)
 
500° F. 
.016–.018” high (.40–.45 mm)
2. To check the parallel alignment of “spider–insert” couplings, 
place a straight edge across both hubs at four points, 90° apart 
(see Fig. 3). To check the parallel alignment of flexible spacer 
couplings,  place  a  dial  indicator  on  one  hub  and  rotate  that 
hub 360° while taking readings on the outside diameter of the 
other hub. Alignment occurs when indicator deflection does 
not exceed .002” T.l.R. (see Fig. 4) of the recommended cold 
setting in elevation and not more than .002” T.l.R. side to side.
To check angular alignment of a “spider–insert” coupling, use 
calipers at 90° intervals on the circumference on the outer end 
of hubs. When caliper measurements are identical, the unit is 
in  angular  alignment.  The  correct  gap  between  the  hub  and 
insert will be given in the coupling manufacturer’s instructions 
supplied for the pump.
To check angular alignment of flexible spacer couplings, place 
a dial indicator on one shaft hub and rotate the hub 360°. Take 
readings from the face of the other hub. Alignment is achieved 
when deflection does not exceed .002” (see Fig. 5).
Figure  2
WEDGES