Page 8-614
test maintenance
8
For the EPN maintenance circuit pack, the SAT interface, EI link, reset and sanity
functions are tested. The long test resets the EPN maintenance circuit pack
causing the EPNSAT link to be dropped and is destructive.
functions are tested. The long test resets the EPN maintenance circuit pack
causing the EPNSAT link to be dropped and is destructive.
Defaults
The default for the parameters are short with a repeat of 1.
Parameters
Help Messages
If the system technician presses
HELP
after entering "test maintenance", the
following message will be displayed:
Enter [cabinet(2-3)];carrier(A)],
[’long’ or ’short’], [’repeat’(1-100)
or ’clear’], [’schedule’]
location
The location designates the physical position of the desired
maintenance circuit pack. The location consists of a cabinet number
and carrier letter. The cabinet number is one or two digits from 2 to 3
with leading zeros allowed.
maintenance circuit pack. The location consists of a cabinet number
and carrier letter. The cabinet number is one or two digits from 2 to 3
with leading zeros allowed.
short
This will cause the command to execute a series of nondestructive
diagnostic tests.
diagnostic tests.
long
This will execute a more comprehensive and longer version of the
diagnostic tests. This includes both destructive and nondestructive
tests for this command.
diagnostic tests. This includes both destructive and nondestructive
tests for this command.
repeat number
The "number" specifies how many times each test in the sequence is
to be repeated. "Number" may be any integer between 1 and 100.
to be repeated. "Number" may be any integer between 1 and 100.
clear
This option causes the test sequence (short or long) to repeat until the
alarm (if one exists against the maintenance object) is cleared or a
single test in the sequence fails. If no alarms are registered against
the maintenance object then the test sequence will be exercised only
once. The long clear option forces a clear of all alarms if no errors are
encountered during testing. The short clear option only clears alarms
pertinent to tests in the short sequence.
alarm (if one exists against the maintenance object) is cleared or a
single test in the sequence fails. If no alarms are registered against
the maintenance object then the test sequence will be exercised only
once. The long clear option forces a clear of all alarms if no errors are
encountered during testing. The short clear option only clears alarms
pertinent to tests in the short sequence.
schedule
When the "schedule" option is specified, the command is validated
and then a scheduling form is displayed to allow the technician to
schedule execution of the command. The command is then placed in
the command queue and is executed at the specified time. The
information displayed by the command is sent to the system printer
instead of the screen. Refer to the Report Scheduler and System
Printer feature specification [1] for more details.
and then a scheduling form is displayed to allow the technician to
schedule execution of the command. The command is then placed in
the command queue and is executed at the specified time. The
information displayed by the command is sent to the system printer
instead of the screen. Refer to the Report Scheduler and System
Printer feature specification [1] for more details.