InfraStruXure Site Planning, Installation, Start-Up
Electrical Requirements and Specifications
Procedures requiring a licensed electrician
Electrical requirements
A licensed electrician must connect utility power. The following procedures 
require a licensed electrician:
• connection of utility conductors
• installation of a 200- or 100-amp circuit breaker
• connection to the main input switch
• connection to a branch circuit
See also
To connect utility power, see the utility connection instructions included with your 
documentation.
200V Input
415V Input
Service distribution breaker 
1,2
200A
100A
Conductors to Main Input switch
1
3W + G
3W + G
Recommended wire sizing
2,3
L1, L2, L3
60mm
2
38mm
2
G
14 mm
2
8 mm
2
1
 Provided by customer
2
 Consult national and local codes for requirements specific to your installation.
3
 CV or CVT cable