Desktop Installation
To install a switch on a desktop:
1. Remove the backing from the four adhesive rubber pads and 
apply the pads to the underside of the switch. Ensure pads are 
aligned with the scribed circles at each corner.
2. Position the switch on a table or desktop as directed by the 
customer. Ensure:
— A grounded AC electrical outlet is available.
— Adequate ventilation is present, and areas with excessive heat, 
dust, or moisture are avoided.
— All planning considerations are met. Refer to McDATA 
Products in a SAN Environment - Planning Manual (620-000124) 
for information.
3. Verify all field-replaceable units (FRUs) are installed as ordered.
4. Connect the AC power cord to the receptacle at the rear of the 
chassis.
5. Connect the AC power cord to a facility power source that 
provides single-phase, 100 to 240 volt alternating current (VAC) 
current.
6. When the power cord is connected, the switch powers on and 
performs power-on self-tests (POSTs). During POSTs:
a. The green power (PWR) LED on the front panel illuminates.
b. The amber system error (ERR) LED on the front panel blinks 
momentarily while the switch is tested.
c. The green LED associated with the Ethernet port blinks 
momentarily while the port is tested.
d. LEDs associated with Fibre Channel ports blink momentarily 
while the ports are tested.
7. After successful POST completion, the PWR LED remains 
illuminated and all other front panel LEDs extinguish.