How to Operate – 
Beer Pump Panels 
 
Adjust primary CO
2
 regulator by turning  
adjusting screw counterclockwise until it turns 
freely, then turn hand valve counterclockwise  
on CO
2
 cylinder to the fully open position. Next, 
turn regulator adjusting screw clockwise until 
required system pressure plus an additional 15 
psig is reached.
Note: If CO
2
 is only being used for keg-    
  applied pressure, adjust to approximately  
40 psig. 
Note: If using air to drive beer pumps,  
adjust the air compressor output regulator 
pressure to a minimum of 15 psig. greater 
than the maximum required system  
pressure required to operate the beer 
pumps. maximum setting 100 psig.
 
Adjust secondary CO
2
 regulator which  
supplies the keg pressure located on the  
beer pump panel to the proper pressure  
setting. Setting depends on beer brand and  
temperature. Desired goal is to maintain the  
natural carbonation in the beer. Open the shut- 
off valves.
 Ensure the Probe Valve on the Perlick Smart 
Coupler is in closed position. See figure 1
Ensure the Beer Pump Flow Reversal/Dispense  
handle is in the dispense position. Adjust the 
Secondary Air/ CO
2
 regulator located on the 
beer pump panel to a minimum operating  
pressure of 10 psig.
 Connect the coupler to a regulated water supply 
with pressure less than 30 psig. 
Note: Pump 
damage may occur with pressure higher 
than 30 psig.
 Open the water supply. Then open probe valve 
on Perlick Smart coupler to the 45° position. 
See figure 2. The beer pump will slowly pump 
up the beer line in the trunk housing to set psig. 
Note: If pump continues to run for longer than 
expected, check lines for possible leaks at one 
or more of the connections.
 Gradually increase secondary regulator  
pressure to the designed system pressure to 
achieve a flow rate of one gallon per minute 
from the dispensing head. 
Note: maximum 
beer pump operating pressure is 90 psig.
 Open dispensing head faucet to purge air 
trapped within the tubing.
 Check all gas and liquid line fittings and  
connections for leaks.
 Close probe valve on Perlick Smart Coupler. 
(See figure 1) and disconnect coupler from  
regulated water source.
Clean beer system. After cleaning and rinsing  
 
the system, make sure the beer line is full of  
 
cold water (beer dispensing from warm beer  
 
lines will be poor quality).
 Tap fresh keg with Perlick Smart Coupler. Open 
dispensing head faucet until clear beer flows.
Figure 1
Closed Position
Figure 2
45° or Cleaning Position
Figure 3
Open Position
Smart Coupler Probe Valve Lever Positions