11 (Optional) Installing the EXD3902 and Cables 
 
Issue 08 (2016-05-30) 
Huawei Proprietary and Confidential         
Copyright © Huawei Technologies Co., Ltd. 
233 
 
Table 11-2 lists the check items of the signal cable connection. 
Table 11-2
 Checklist for the signal cable connection 
No. 
Item 
The signal cable connectors are securely connected. 
The signal cable connectors are intact.   
The signal cables are intact.   
The signal cables are bound neatly with cable ties to proper tightness, and 
arranged at even intervals in the same direction.   
The excess of cable ties is trimmed off without remaining rough edges. 
The signal cable layout facilitates future maintenance and capacity expansion.   
Labels at two ends of the signal cables are correct and legible. 
 
Table 11-3 lists the checking items for other cable connections. 
Table 11-3
 Checklist for other cable connections 
No. 
Item 
The connectors of the other cables are securely connected. 
All labels on the cables are legible and are bound according to the engineering 
requirements. The cables are bound tightly and neatly. The sheaths of the 
cables are intact. 
The cable layout complies with the engineering design. 
There are no connectors or joints on each PGND cable. None of PGND cables 
can be short-circuited or reversely connected. In addition, these cables are not 
damaged or broken. 
PGND cables are separately bound from other cables. 
The protection grounding of the EXD3902 and the surge protection grounding 
of the building share one group of ground conductors.   
 
11.7 Powering on the EXD3902 
This section describes the power-on check on the EXD3902 after the EXD3902 hardware is 
installed and checked. 