Commissioning the RT   7–17
RT installation
After acquiring the HT, the CCM automatically loads its software
and  configuration data and becomes operational. This is indicated
by 
RT Enabled
 on the LCD.
Before performing the RT to HT connection tests described in 
section 7.9, make sure the LCD shows:
RT       Freq 8B4
Enabled
(Frequency is 
specific to RT)
The 
RT Enabled
 message indicates that the equipment is
operational.
If SSIs are installed but not yet configured through the EMS, the
operational status will be 
RT Disabled
.
The possible operational states are:
Enabled
RT is ready for service.
Disabled
Equipment is operational, but RT
is not ready for service.
Degraded
One or more components is not
fully operational.
Enabled
Degraded
RT is ready for service, but one
or more components is not fully
operational.
Enabled 
In Test
All of the RT’s SSIs are in test
mode.
At this point, RT commissioning is complete, except for the RT to
HT tests described in section 7.9. You may or may not be able to
complete these tests, depending on whether or not other network
components are installed and operational. (See the test
requirements listed in section 7.9.)
Leave the RT powered on for testing and operation.
7.8
Verifying the RT’s
operational state