Tyco SafeLINC 4100U Manual Do Utilizador

Página de 180
 
 
11-4 
 
 
 
To place the 4100U FACP into operation, perform the following steps: 
 
STEP 1 
Ensure that the Mains Isolate Switch is OFF. 
 
STEP 2   
Ensure that 240 VAC is connected to the panel from the mains distribution 
 switchboard. 
 
STEP 3 
Ensure that the Lithium battery is fitted to battery holder on the CPU card, 
and link  
 
P3 is fitted to the BAT ON position. 
 
 
Turn the Mains Isolate Switch ON. 
 
STEP 4 
Check that the green "MAINS ON" LED indicator is on. 
 
The Controller performs tests on its memory, electronics, and the LCD. 
 
STEP 5 
Check that the buzzer sounds and the LCD display “CPU Serial Number”. 
 
STEP 6 
Check that the LCD has good visibility.   
 
STEP 7 
Install and connect the batteries.   
 
Take care not to short the battery leads or connect in reverse polarity when 
 connecting. 
 
STEP 8 
Press the Lamp Test key on the Operator I/F and check that all LEDs turn 
on, and  
 
the LCD shows all black squares. 
 
STEP 9 
Clear all faults one at a time.  
 
A full commissioning test should be carried out as per AS1670.1. Refer to the appendix in 
this manual for detail on checking wiring, and earth fault detection. Refer to the 
Operator’s Manual LT0351 for detail of the walk test that may be used for verifying 
correct detector operation. 
 
 
 
 Power Up & Placing into Operation