5. Line Set Installation
Precharged factory line sets, available as optional equipment from Hoshizaki America, 
are recommended. For details, see "II.G.5.a) Factory Line Set Installation." Field 
fabricated line sets are allowed. For details, see "II.G.5.b) Field Fabricated Line Set 
Installation."
a) Factory Line Set Installation
1) Route the factory line set (see "II.G.4 Line Set Size and Refrigerant Charge" for 
details) from the remote condenser unit to the icemaker. Leave a service loop behind 
the icemaker to allow the icemaker to be pulled out for service. See Fig. 12. Factory 
fabricated line sets are precharged and do not need to be evacuated. If the line set is 
too long or too short, see "II.G.5.a)(1) Factory Line Set Modification." 
NOTICE
• Ensure that there are no traps and no kinks in the line set. The service loop is not 
considered an oil trap.
• Do not coil extra line set.
2) Connect the refrigerant lines to the appropriate male fittings on the remote condenser 
unit first and then at the icemaker. Make a proper connection as follows:
a. Remove the protective covers from the male fitting and female coupling.
b. Apply Polyol Ester (POE) refrigerant oil or Parker Super O Lube to the entire male 
fitting, including O-ring, diaphragm, and threads before making the connection. 
See Fig. 13. 
NOTICE! Do not use thread sealant on the fittings. Use POE 
refrigerant oil or Parker Super O Lube only.
c. Make sure the male fitting and female coupling are properly aligned, then start the 
connection by hand to ensure that it is not cross threaded. 
d. Tighten the connection with a wrench until it is tight. At this point, the nut has 
covered most of the threads on the male fitting. 
e. Mark a reference line on the female coupling and the remote condenser unit or 
icemaker panel. Using a backup wrench on the back of the female coupling, tighten 
the six-sided nut of the female coupling an additional 1/6 turn. See Fig. 14.
3) If you lengthened the line set as outlined in "II.G.5.a)(1) Factory Line Set Modification" 
and it exceeds 66 feet, see "II.G.4. Line Set Size and Refrigerant Charge" for proper 
charging of the appliance.
(1) Factory Line Set Modification
1) Recover the line set charge through the Schrader access ports on the Parker quick 
connect couplings and store it in an approved container. Do not discharge the 
refrigerant into the atmosphere. Remove the extra line set length or add extra tubing. 
When adding extra tubing, insulate the additional copper tubes separately.
2) Use an electronic leak detector or soap bubbles to check for leaks. Add a trace 
of refrigerant to the lines through the Schrader access ports on the Parker quick 
connect couplings (if using an electronic leak detector), and then raise the pressure 
using nitrogen gas (140 PSIG). 
WARNING! Do not use R-404A as a mixture with 
pressurized air for leak testing.