Middleby Marshall Model PS536 Manual Do Utilizador

Página de 84
11
ENGLISH
Figure 2-8 - Assembling and tensioning the conveyor
Tensioning
screws in slotted
holes (2 per side)
With tensioning
screws loosened,
frame  sections  can
be moved to adjust
belt tension
1-2" (25-50mm)
vertical  deflection
Figure 2-9 - Conveyor and Master Link Orientation
Direction
of  travel
CORRECT
master link
position
Incorrect
master link
position
SECTION 2 - INSTALLATION
Pins on frame
fit  into  slots
on bracket
D. Conveyor Installation
1. Unfold the conveyor frame so that it lies flat on the floor.  As
you unfold the frame, check that the locator pins shown in
Figure 2-8 lock into the slots on the bracket.
2. Refer to Figure 2-8.  Note the locations of the four tensioning
screws (2 per side) in the slotted holes on the brackets.
Loosen these screws to allow the conveyor to be properly
tensioned.
3. Lift the conveyor belt away from the frame, as shown in
Figure 2-8, to check the belt tension.  The belt should lift
between  1-2"  (25-50mm).
If it is necessary to adjust the belt tension, gently push the
two  conveyor  frame  sections  closer  together,  or  further
apart,  as  required.    Then,  re-check  the  tension  of  the
conveyor  belt.    Repeat  this  step  as  necessary  until  the
proper belt tension is achieved.
4. When the belt tension is correctly adjusted, tighten the two
tensioning  screws  on  each  side  of  the  conveyor  frame.
This fastens the two frame sections together at the correct
belt  tension.
5. If it is necessary to add or remove conveyor links to achieve
the  correct  tension,  OR  if  it  is  necessary  to  reverse  the
conveyor belt for correct orientation, the belt will need to be
removed  from  the  conveyor  frame.    If  this  is  necessary,
perform  the  following  procedure:
a. Remove  the  master  links  using  long-nose  pliers.
Then, roll up the belt along the length of the conveyor
frame.
b. Add or remove belt links as necessary to achieve the
correct belt tension.
c. Replace the belt on the conveyor frame.  Check the
following:
•
The conveyor belt links must be oriented as shown
in Figure 2-9.
•
The smooth side of the conveyor belt must face
UP.
d. Connect the inside master links.  Check that the links
are oriented as shown in Figure 2-9.
e. Connect  the  outside  master  links.    Note  that  the
outside master links each have an open hook on one
side.  This hook aligns with the hooks along the sides
of the other conveyor links.  See Figure 2-9.
Folded
frame