SECTION 2 - INSTALLATION
VI. ELECTRICAL SUPPLY
WARNING
Authorized supplier personnel normally accomplish
the connections for the ventilation system, electric supply,
and gas supply, as arranged by the customer.  Following
these  connections,  the  factory-authorized  installer  can
perform the initial startup of the oven.
NOTE:  
The  electric  supply  installation  must  satisfy  the
requirements of the appropriate statutory authority, such as the
National  Electrical  Code  (NEC),  ANSI/NFPA70,  (U.S.A.);  the
Canadian  Electrical  Code,  CSA  C22.2;  the  Australian  Code,
AG601;  or  other  applicable  regulations.
NOTE:  The electric supply connection must meet all national
and  local  electrical  code  requirements.
Check the oven serial plate before making any electric supply
connections. Electric supply connections must agree with data
on the oven serial plate.  The location of the serial plate is shown
in Figure 1-1 (in Section 1, Description).
A fused disconnect switch or a main circuit breaker
(customer furnished) MUST be installed in the electric
supply line for each oven cavity.  It is recommended
that  this  switch/circuit  breaker  have  lockout/tagout
capability.
The  supply  conductors  must  be  of  the  size  and
material (copper) recommended.  Refer to the wiring
diagram  inside  the  machinery  compartment  of  the
oven.  Electrical specifications are also listed on the
oven's serial plate and in Tables 1-3 and 1-4, Elec-
trical Specifications (in Section 1, Description).
The oven requires a ground connection to the oven
ground screw located in the electrical junction box.
(The box is shown in Figure 2-13.)  If necessary, have
the electrician supply the ground wire.  Do NOT use
the  wiring  conduit  or  other  piping  for  ground
connections!
A. Additional Information - Gas Ovens
All electric supply connections are made at the
terminal block located in the electrical junction
box, shown in Figure 2-13.  The power lines then
connect  to  the  oven  circuits  through  a  safety
switch  located  inside  the  machinery  compart-
ment.  This switch interrupts electric power to the
oven when the Machinery Compartment Access
Panel  is  opened.
B. Additional Information - Electric Ovens
A 1.3" (33mm) dia. cutout in the back wall of the machinery
compartment  provides  access  to  the  electrical  supply
connections.  The actual wiring connections are made at
the terminal block located in the electrical junction box.
Using  flexible  cables  for  the  electric  power  supply
conductors requires a 1.3" (33mm) strain-relief fitting (not
furnished  with  the  oven)  to  enable  safe  access  to  the
terminal  block.
C. Connection
Refer  to  the  wiring  diagram  inside  the  machinery
compartment  of  the  oven  to  determine  the  correct
connections  for  the  electrical  supply  lines.    Connect  the
supply as indicated on the wiring diagram.
Electrical
Junction Box
1.3" (33mm) cutout for
electric  utility  connection
(electric  ovens  only)
Figure 2-13 - Utility connection locations
VII. GAS SUPPLY
CAUTION
DURING PRESSURE TESTING NOTE ONE OF THE FOLLOWING:
1. The oven and its individual shutoff valve must be discon-
nected  from  the  gas  supply  piping  system  during  any
pressure testing of that system at test pressure in excess
of 1/2 psi (3.45 kPa).
2. The oven must be isolated from the gas supply piping
system by closing its individual manual shutoff valve dur-
ing any pressure testing of the gas supply piping system at
test pressure equal to or less than 1/2 psi (3.45 kPa).
3. If incoming pressure is over 14” W.C. (35mbar), a sepa-
rate regulator MUST be installed in the line BEFORE the
individual shutoff valve for the oven.
WARNING: 
To prevent damage to the control valve regula-
tor during initial turn- on of gas, it is very important to open
the manual shutoff valve very slowly.
After the initial gas turn-on, the manual shutoff valve must
remain open except during pressure testing as outlined in
the above steps or when necessary during service main-
tenance.
1/2" NPT pipe for gas
utility  connection
(gas  ovens  only)