Справочник Пользователя для Majestic Appliances 33LDVR

Скачать
Страница из 40
17
LDVR Series Direct Vent Gas Fireplace
10007317
STEP 6
Apply high temperature sealant to 4” (102 mm) and 7” 
(178 mm) collars or the termination one inch away from 
the end. Guide the vent terminationʼs 4” and 7” collars 
into their respective vent pipes. Double check that the 
vent pipes overlap the collars by 2” (50 mm). Secure the 
termination to the wall with screws provided and caulk 
around the wall plate to weatherproof. (Fig. 30)
STEP 7
Support the horizontal pipes every 36” (914 mm) with 
metal pipe straps. Make sure that the horizontal vent 
pipe is installed on a level horizontal plane.
STEP 8
Re-check the fireplace to make sure that it is levelled, 
properly positioned, and nailed or screwed to the floor. 
If applied, the fireplaces adjustable frame drywall strips 
(nailing flanges) should be fastened. Refer to “Framing 
& Finishing”.
CFM137
Rear Vent length
2/26/01   sta
X
High 
Temperature Sealant
CFM137
Fig. 29  Apply high temperature sealant.
CFM138
4", 7" collar
2/26/01   sta
X
X
CFM138
Fig. 30   Horizontal length requirement.
CFM136
Rear Vent horizontal length
2/26/01  sta
X
Always install hori-
zontal venting on a 
level plane.
CFM136
Fig. 28  Measure horizontal length including 2” overlap.
Below Grade Installations
When it is not possible to meet the required vent ter-
minal clearances of 12” (305mm) above grade level a 
snorkel vent kit #7TDVSNORK is required.  It allows 
installation depth of down to 7” (178 mm) below grade 
level.  The 7” is measured from the center of the hori-
zontal vent pipe as it penetrates through the wall.
If venting system is installed below 
ground, we recommend a window well with 
adequate and proper drainage.
Ensure sidewall venting clearances are observed.
The maximum horizontal run with 24” 
vertical rise is 36” (914 mm) from the 
back of the fireplace to the face of the 
exterior wall. See vent graph (Page 12)  for 
extended horizontal run if the vertical rise 
exceeds 24” (610 mm).
1.  Establish vent hole through the wall. (Fig. 25)
2.  Remove soil to a depth of approximately 16” 
(406mm) below base of snorkel. Install window 
well (not supplied). Refill hole with 12” (305 mm) of 
coarse gravel leaving a clearance of approximately 
4” (102 mm) below snorkel. (Fig. 31)
3.  Install vent system. See Page 13, Steps 2 through 5.
4.  Ensure a watertight seal is made around the vent 
pipe coming through the wall.
5.  Apply high temperature sealant caulking (supplied) 
around the 4” and 7” snorkel collars.
6.  Slide into the vent pipe and secure to the wall.
7.  Level the soil to maintain a 4” (102 mm) clearance 
below snorkel. (Fig. 31)