PROTECT C. with 2 battery expansions
Fig.: PROTECT C. 1000 and two C. 1000BP
1.
Check  the  correct  fit  of  the  UPS  and  the  battery 
unit  (the  casings  e.g.  have  to  have  the  same 
dimension).
2.
Now 
connect 
the 
corresponding 
battery 
connectors  using  the  supplied  battery  connection 
cables  as  shown  in  the  figure  above.  When 
connecting,  make  sure  that  you  push  the  plug 
quickly and firmly in the battery connectors.
5.2.1
Electrical Start-Up
Verify  that  UPS  voltage  of  your  country  corresponds  to  your 
equipment voltage. The default setting is set to 230 V. Output 
voltage on the UPS system can be adjusted with the software 
“CompuWatch” in steps of 220 Vac, 230 Vac and 240 Vac.
Turn on the PROTECT C. to the mains
1.
Now  connect  the  input  of  the  UPS  to  the  mains 
connection  cable  provided  and  plug  the  mains 
connector  into  a  suitable  shockproof  socket.  Avoid 
using  extension  cables  and  /  or  adapters. In 
particular in  the case of  high-capacity  types,  ensure 
that  the  fusing  in  your  sub-distribution  is  adequately 
dimensioned: The 3kVA system for example requires 
its own connection with a 16 A fuse. No other loads 
should be connected to this circuit!
2.
Activate  the  mains  input  circuit  breaker.  If 
necessary switch it to “ON”.