  Planning for RF Deployment
Voice/Deployment
 shows the voice network pattern and overlap.
Figure 3-5
Single Floor Site Survey for Voice
The APs are grouped closer together and have more overlap than a data-only installation, because voice 
clients should roam to a better AP before dropping packets. You generally also want to run smaller cells 
than in the past, and ensure the overlapping cell edges at or above -67 dBm. This accomplishes a number 
of things including greater homogeneity across a single cell and reducing processor load in the handheld, 
which increases link stability and reduces latency. Although only one AP might be required for a defined 
area, Cisco recommends that you have two APs on nonoverlapping channels with a received signal 
strength indication (RSSI) above 35 at all times in your installation, for redundancy and load balancing 
purposes. For the 7920 voice deployment, Cisco recommends that you have a Received Signal Strength 
Indication (RSSI) above 35 at all time in your installation. This is to ensure that the VoIP phone has good 
reception as well as allowing some over-subscription and enhances roaming choices for the phone.
Remember that designing for low noise background is as important as relatively high energy density 
within the cell. This means that a good baseline power setting for the AP is in the 35–50 mW range. This 
generally requires approximately 15 percent more APs than if you deployed a coverage model at 
100 mW. 
Pre-site surveys are useful for identifying and characterizing certain challenging areas and potential 
sources for interference, such as existing WLANs, rogues, and non-802.11 interference from sources 
such as microwave ovens and many cordless telephones. Following a design that should be reviewed and 
approved by all stakeholders, post-site surveys should be considered as an excellent audit mechanism to 
ensure that the coverage model complies with the intended functional requirements as set forth by the 