4.3  COMMISSIONING PROCEDURE 
System commissioning can commence after the monitoring system has completed self initialization. The 
commissioning procedure is shown below: 
 
 
Connect and inquiry status
Set channel No.
Input power detection and adjust the direction of 
Donor Antenna
Output power confirmation
Drive test and adjust the direction of Service 
Antenna
Adjust UL ATT and confirm the call quality 
Double check the status of BTS Uplink and the isolation 
between Donor Antenna and Service Antenna 
End
Set monitor parameters
Isolation detection
 
 
 
Figure 24: Commissiong Flow Chart