Installation completion
Chapter 4: What’s Next
Table 4-1
Installation completion checklist (Continued)
Status
No.
Item
Notes
13
Cable racks properly grounded.
14
Static wrist straps are present.
15
Site cleaned, swept, and trash removed.
16
Any deficiencies reported to the
appropriate people.
17
Correct polarity has been maintained
from the DC power source to the frame.
18
Power has not been applied to any frame.
Record “As-Built” information
Record the site specific information on how the unit was installed and cabled.
Performing the ATPs
This manual does not cover the procedure of performing the ATPs. For this procedure, refer to
the
1X UBS Macro BTS Optimization/ATP
(68P09283A63) manual.
Loading the software
This manual does not cover the procedure for loading the software. Refer to the appropriate
software release manual for procedure for loading the software.
4-4
68P09283A62-2
PRELIMINARY
AUG 2007