Справочник Пользователя для HP Performance Optimized Data Center (POD) 40c
Power up procedure 68
This process ensures personnel safety during the electrical start up of the HP POD 40c G2.
WARNING:
To avoid risk of personal injury or loss of life, do not open an energized POD
electrical cabinet without an energized work permit and appropriate PPE.
Cold weather power up checklist
Site electrical
Verify that all POD site power feeder breakers are open.
POD electrical
Verify that all POD site power feeder breakers are open.
POD electrical
•
Hot aisle
Verify that all IT power drop box breakers located on the power tap boxes are open.
Verify that all IT power drop box breakers located on the power tap boxes are open.
•
Cold aisle
a.
Close all breakers and fuses within the control cabinet.
b.
Close and latch the ECS cabinet with the supplied T-handle.
c.
Position the EPO system to Armed (White) or Bypass (Green) using the EPO key control on the door
to the control cabinet.
to the control cabinet.
d.
Verify that the EPO buttons are in the reset position (not depressed).
•
IT critical power feed cabinets A and B
a.
Close all fuses in power cabinets A and B.
b.
Close all non-spare breakers in power cabinets A and B.
c.
Close and lock power cabinet doors A and B.
d.
Close and lock the fire suppression cabinet door.
Cold weather power up procedure
Perform the following procedures in the exact order in which they are listed.
Site electrical
Close all POD site power feeder breakers and monitor for any effects that are not standard.
Site chilled water
1.
Open the POD supply chilled water isolation valve.
2.
If necessary, vent the air from the chilled water return header.
3.
Open the POD return chilled water isolation valve.
4.
Verify audible flow noises are present.