Power up procedure  68 
This process ensures personnel safety during the electrical start up of the HP POD 40c G2. 
  
 
WARNING:
  To avoid risk of personal injury or loss of life, do not open an energized POD 
electrical cabinet without an energized work permit and appropriate PPE. 
  
 
Cold weather power up checklist 
Site electrical 
Verify that all POD site power feeder breakers are open. 
POD electrical 
 
Hot aisle 
Verify that all IT power drop box breakers located on the power tap boxes are open. 
 
Cold aisle 
a. 
Close all breakers and fuses within the control cabinet. 
b. 
Close and latch the ECS cabinet with the supplied T-handle. 
c. 
Position the EPO system to Armed (White) or Bypass (Green) using the EPO key control on the door 
to the control cabinet. 
d. 
Verify that the EPO buttons are in the reset position (not depressed). 
 
IT critical power feed cabinets A and B 
a. 
Close all fuses in power cabinets A and B. 
b. 
Close all non-spare breakers in power cabinets A and B. 
c. 
Close and lock power cabinet doors A and B. 
d. 
Close and lock the fire suppression cabinet door. 
 
Cold weather power up procedure 
Perform the following procedures in the exact order in which they are listed. 
 
Site electrical 
Close all POD site power feeder breakers and monitor for any effects that are not standard. 
 
Site chilled water 
1. 
Open the POD supply chilled water isolation valve. 
2. 
If necessary, vent the air from the chilled water return header. 
3. 
Open the POD return chilled water isolation valve. 
4. 
Verify audible flow noises are present.