5.4 Starting Monitoring
5.4 Starting Monitoring
This section describes how to perform monitoring with the project data monitored previously.
1
Perform either of the following operations.
• Click
(Monitor
Start)
• Select [Online]
[Monitor Start] from the menu.
• Right-click the mouse and select [Monitor Start] from the menu.
2
Monitoring is started with the project data monitored previously.
Before monitoring
The following shows the procedure used when not starting monitoring with the
project data monitored previously.
project data monitored previously.
(1) When performing a monitoring for the first time
Select [Project]
[Open] and set a project data to be monitored.
When performing a monitoring for the first time, performing the operation shown in
this section causes GT SoftGOT1000 to display the Utility.
this section causes GT SoftGOT1000 to display the Utility.
(2) When project data has been changed after previous monitoring
Select [Project]
[Open] and set the project data to be monitored before starting