Справочник Пользователя для Lucent Technologies Release 8.2
Configuration 5B: R8csi <—ppp—> R8r (2 C-LANs)
<—ethernet—> R8si
<—ethernet—> R8si
191
Administration for Network Connectivity
555-233-504 — Issue 1 — April 2000
CID: 77730
3
C-LAN Administration
Switch 2 Task — Assign Link via ppp Data Module to Switch 1
This task administers a ppp data module on Switch 2 for the ppp connection to Switch
1. The data module associates a link number with a port address, extension number,
and node name for the C-LAN port used for this connection.
1. The data module associates a link number with a port address, extension number,
and node name for the C-LAN port used for this connection.
Begin
Steps
>
Open Data Module form — enter
ad da 3020
> Enter values
add data-module 3020
Page 1 of x
Page 1 of x
DATA MODULE
Data Extension: 3020 Name: _ppp on link 1 to node-1a-ppp BCC: 2
Type: ppp
Type: ppp
COS: 1
Port: 01a0413 COR:
1
Link: 1_
TN: 1
Enable Link? n
Node Name: node-2___
_
Subnet Mask: 255.255.255.0
Establish Connection: n
DESTINATION
Digits:
Digits:
__________
Node Name: node-1a-ppp______
CHAP? n
Field
Conditions/Comments
Type:
This indicates the data-module type for this connection.
Port:
In this example, the C-LAN circuit pack is in slot 01a04; the ppp
connection is through port 13.
connection is through port 13.
Link:
The link number must be in the range 1 – 25 (for R8csi), not
previously assigned on this switch
previously assigned on this switch
Enable Link?
If you need to add an IP route that uses this node as a gateway,
this field must be set to
this field must be set to
y
before adding the IP route. Otherwise
leave this field set to
n
until the link administration is complete;
that is, until after all data modules and the processor channels
are assigned, then set to
are assigned, then set to
y
.
Name:
Information-only; appears in list generated by the “list data
module” command.
module” command.
BCC:
Bearer Capability Class. This is a display-only field.
1 of 2