Overview 
3  
C-LAN Administration
Administration for Network Connectivity
CID: 77730
555-233-504 — Issue 1 — April 2000
54
Checklist for Prerequisite Administration
This is a checklist of things that need to be completed before you can proceed with the 
network administration tasks. Review this checklist before starting the administration 
tasks. 
Checklist Item
The prerequisite administration needed depends on whether the system is new or 
is being upgraded from an R7 or pre-R7 system to R8. Use the following map to 
determine which steps to perform.
For more information about the checklist items, refer to Appendix A or the 
appropriate upgrades book in "References", 
UPGRADES ONLY:
 Steps 1–6 apply only to systems being upgraded to R8 
from an R7 or pre-R7 release. For new systems, skip to step 7.
1  
Save translations on customer flash card (csi or si models) or tape (r 
model). For R7 systems, skip to step 5.
2  
This step is for the si model only. It preserves ISDN-PRI connections, 
which (for R7 and later) are carried on the NetPkt circuit pack instead of 
the PI or PACCON circuit packs. ISDN-PRI connections are preserved 
transparently on the csi and r models.
If:
the si switch has existing ISDN-PRI connections that the customer wants to 
keep, complete the following steps:
~
De-administer the ISDN-PRI connections:
busy the ISDN links
remove comm-interface links of type ISDN
remove comm-interface processor channels that use ISDN links
remove data modules using those links
~
Save translations on a “working” flash card
Otherwise:
skip to step 3.
1 of 3
1 2 3  4 5 6 7 
New
R7
Pre-R7 si with
Other Pre-R7
ISDN connections
to be preserved