3. EXAMINATION 
A. Examination 
(1) 
Examine ducts, air-handling units, and conditions for compliance with requirements 
for installation tolerances and other conditions affecting performance. 
(2) 
Examine roughing-in for piping systems to verify actual locations of piping 
connections before humidifier installation.  
(3) 
Proceed with installation only after unsatisfactory conditions have been corrected. 
B. Installation 
(1) 
Install humidifiers and steam dispersion panels per manufacturers’ instructions. 
(2) 
Seal humidifier dispersion-tube duct penetrations with flange. 
(3) 
Install with required clearance for service and maintenance. 
C. Testing 
(1) 
System verification testing is part of the commissioning process. Verification testing 
shall be performed by the Contractor and witnessed and documented by the 
Commissioning Authority.  Refer to section 01810, Commissioning, for system 
verification tests and commissioning requirements. 
 
XXXXX  OR  XXXXX 
(2) 
Manufacturer’s Field Service:  Engage a factory-authorized service representative 
to inspect field-assembled components and equipment installation, including piping 
and electrical connections.  Report results in writing. 
(a) 
Leak Test:  After installation, charge system and test for leaks.  Repair leaks 
and retest until no leaks exist. 
(b) 
Operational Test:  After electrical circuitry has been energized, start units to 
confirm proper unit operation.  Remove malfunctioning units, replace with 
new units, and retest. 
(c) 
Test and adjust controls and safeties.  Replace damaged and malfunctioning 
controls and equipment.