Crown Boiler 24-03 用户手册

下载
页码 90
51
sufficiently to permit a steady trickle of water 
from the surface blowoff pipe.  Continue this 
slow boiling and trickle of overflow for several 
hours until the water coming from the overflow 
is clear.
d.  Stop burner and drain boiler in a manner and to 
a location that hot water can be discharged with 
safety.
e.  Refill boiler to normal water line.  If water in 
gauge glass does not appear to be clear, repeat 
steps (a. thru e.), and boil out the boiler for a 
longer time.
2.  Low pressure steam boilers such as the Series 
24 should be maintained with appropriate water 
treatment compounds.  After cleaning process has 
been completed, add water treatment compounds 
as  recommended by your local qualified water 
treatment company. 
3.  Remove temporary surface blowoff piping and 
replug tapping.  Boil or bring water temperature to 
180°F promptly in order to drive off the dissolved 
gases in the fresh water.
4.  If unsteady water line, foaming or priming persist, 
install gate valve in Hartford Loop and drain valves 
in return main and at boiler and proceed as follows:
a.   Connect hoses from drain cocks to floor drain.  
Close gate valve in Hartford Loop and open 
drain cock in return main.  Fill boiler to normal 
water level, turn on burner and operate boiler 
at this water level for at least 30 minutes after 
the condensate begins to run hot, then turn off 
burner.
  Close all radiator valves.  Remove all supply 
main air valves and plug the openings in supply 
main.
b.  Draw about 5 gallons of hot water from boiler 
into a container and dissolve into it appropriate 
amount of a recommended boilout compound.  
Remove surface blowoff plug and pour this 
solution into boiler, then reinstall plug.
c.  Turn on burner and keep operating while feeding 
water to boiler slowly.  This will raise water level 
in boiler slowly so that water will be boiling hot 
and will rise slowly into supply main and back 
through return main, flowing from drain hose 
at about 180°F.  Continue until water runs clear 
from drain hose for at least 30 minutes.
d.  Stop feeding water to boiler but continue 
operating burner until excess water in boiler 
flows out through supply main and water lowers 
(by steaming) until it reaches normal level in 
boiler.  Turn off burner.  Drain boiler.  Open all 
radiator valves.  Reinstall all supply main air 
valves.  Open gate valve in Hartford Loop.
e.  When boiler has cooled down sufficiently (crown 
sheet of sections are not too hot to touch), close 
CAUTION
Probe and float type low water cutoff
devices require annual inspection and
maintenance.
4.  CHECK OPERATING CONTROL on boiler 
equipped with tankless heaters.  With burner off, 
draw hot water until burner starts, then turn off hot 
water and check burner shutdown. 
5.  CHECK RTC CONTROL - see the Test Section in 
the RTC Installation and Maintenance Manual.
K.
  BOILER AND SYSTEM CLEANING - STEAM 
BOILER
NOTICE
A qualified water treatment chemical
specialist should be consulted for
recommendations regarding appropriate
chemical compounds and concentrations
which are compatible with local
environmental regulations.
WARNING
Chemicals used in treating boiler water are
toxic and/or harmful.  Always use protective
clothing and equipment when working
with/near chemicals.  Contact local
authorities to determine if treated boiler
water can be discharged into local waste
water system.
1.  Oil, greases & sediments which accumulate in a 
new boiler and piping must be removed in order 
to prevent an unsteady water line and carry over 
of the water into the supply main above boiler.  
Operate the boiler with steam in the entire system 
for a few days allowing the condensate to return 
to the boiler.  If the condensate can temporarily be 
wasted, operate boiler only for the length of time 
it takes for condensate to run clear.  If the latter 
cannot be achieved or if the condensate is returned 
to the boiler, boil out the boiler using the SURFACE 
BLOWOFF connection.  See Figure 40a.
a.  Drain boiler until water is just visible in gauge 
glass.  Run temporarily 1½” pipe line from the 
surface blowoff connection to an open drain or 
some other location where hot water may be 
discharged safely.  Do not install valve in this 
line.
b.  Add an appropriate amount of recommended 
boilout compounds.
c.  Start burner and operate sufficiently to boil 
the water without producing steam pressure.  
Boil for about 5 hours.  Open boiler feed pipe