Installation and Assembly 
Tools required for assembly 
Forklift or hoist with straps/slings 
14mm (or 9/16”) wrench or socket 
Cross-point (Phillips) screwdriver 
3mm and 5mm hex wrenches (provided) 
 
1.  Remove any boards or straps that secure 
the Jointer to the pallet, and remove 
protective wrapping. 
2.  Use a 14mm (or 9/16”) wrench to remove 
the four lag screws at the base of the stand 
which helped secure the machine to the 
pallet. One of these screws is shown in 
Figure 1. 
 The Jointer should be raised 
by straps placed around the four lifting rods 
(see Figure 2). Do NOT lift the machine 
directly beneath the infeed and outfeed 
tables, as this can cause misalignment of the 
tables.  
3.  Pull the four lifting rods out as far as they 
will go and run the straps around the rods 
as shown in Figure 2. Using a forklift or 
hoist, lift the machine off the pallet and into 
its desired location. When the straps are 
removed, push the lifting rods back in. 
4.  The Jointer should be located in a dry area, 
on a sturdy floor, and with sufficient lighting 
and ventilation. Leave plenty of space 
around the machine for operations and 
routine maintenance work.  
5. If desired, the Jointer can be further 
stabilized by securing it to the floor, using 
lag screws through the four holes at the 
base of the stand. 
 
The jointer should be 
disconnected from the power source during 
assembly procedures.
 
6.  Exposed metal areas of the Jointer, such as 
the table and fence surfaces, have been 
factory coated with a protectant. This can be 
removed with a soft cloth dampened with 
kerosene or mineral spirits. Do not use an 
abrasive pad. Do not let solvent contact 
plastic or rubber parts as it may damage 
them.  
  Use caution when cleaning 
around cutterhead. The knives are extremely 
sharp.
 
 
 
Figure 1 
 
Figure 2 
(straps not included)