AEG PV.630 用户手册

下载
页码 128
Protect PV.630 Installation and Start-up 
20 of 21 
80000047963 BAL 
6.3 
Connection of DC Voltage 
GCB  Generator connection box 
Grid  Power utility mains (supplying mains) 
DOU  Display and operation unit 
 
After connecting the DC voltage: 
 Switch off GCBs (external). 
 Check that there is no voltage. 
 Insert all F41 fuses (DC/AC control cabinet). 
 Check the polarity in the system's DC/AC control cabinet. 
 Check the polarity of the DC at every GCB.
 
Connect all GCBs. 
 Switch on the system via the DOU. 
The INV contactor K7 switches on automatically after a few sec-
onds and power is fed into the power utility mains.  
If the INV contactor K7 does not switch on, check the following:  
 
“Field rotation fault” fault message 
Check the INV control cabinet and DC/AC control cabinet connec-
tion lines to ensure they have a clockwise rotating field.  
 Isolate the system to do this. 
 
Other fault indications 
 See “Monitoring Systems, Messages and Faults” in the operat-
ing instructions.