Infrastructure Requirements and Layout Planning 
LTE 700 MHz MobileAccessVE Instant Coverage Solution User Manual 
11
 
3.2 
Infrastructure Requirements 
Ethernet  standards  specify  that  the  maximum  distance  between  an  Ethernet  switch  and  an 
appliance  (computer,  WLAN  AP,  etc)  should  not  exceed  100m  (300ft).  Therefore,  when  VE 
shares  the  IT  LAN,  the  maximum  distance  for  a  given  cable  run  cannot  be  longer  than  100m 
(300ft)  between  the  Ethernet  switch  and  appliance,  including  all  patch  cords  (from  switch  to 
VCU, from VCU to patch panel, from RJ-45 outlet to VAP, and from VAP to appliance). 
Typically the horizontal cabling system will be connected to patch-panels in the communication 
rooms. The entire cabling system, including the patch panels and patch cords, should adhere to 
the CAT-5e/6  standard.  Specifically all pairs  of the  CAT-5e  cable should  be wired  in the patch 
panels and patch cords.  
1.  IDF/Telco closet space for one or more VCUs depending on the number and locations of the 
installed VCUs: (48.3cm x 51.3cm x 8.88cm) per VCU. 
Note: When planning the IDF/Telco shaft, take the RF equipment (picocell/microcell or BDA) 
and the VCU into consideration. 
2.  350 Watts of AC power to the VCU IDF/Telco closet. 
3.  Building infrastructure: 
  CAT-5e/6 cabling, Shielded Twisted Pair (STP) 
  24 AWG minimum diameter for CAT-5e cabling 
  Dedicated  CAT-6/7  STP  cable  from  Master  VCU  to  Slave  VCUs  with  run  lengths  NOT 
exceeding 100m (300ft) and no shorter than 10m (33ft). 
  CAT-5e/6  STP  cable  from  VCU  to  each  VAP  with  run  lengths  NOT  exceeding  100m                                                                                                                                                     
(300ft) and no shorter than 10m (33ft). VAPs can be connected over existing CAT-5e/6 
cabling infrastructure and existing Ethernet jacks without affecting the LAN. 
Note: Verify with the IT department that the existing cables can support the VE installation. 
If available, review the infrastructure documentation to determine cable types and lengths. 
If  the  infrastructure  documentation  is  not  available,  attempt  to  visually  identify  the  cable 
type. Depending on the cable vendor, the cable type may be listed on the cable sheath. It is 
recommended to use a Fluke cable tester to measure  the cable length of the most remote 
VAPs. 
4.  Master VCU Cable Connections:  
  (2) N-type female, 50 ohm interfaces to carrier equipment 
  (Up to 12) RJ-45 interfaces to Slave VCUs and/or VAPs 
  (1) RJ-45 interface to Management 
  (1) D-Type 9 pins RS-232 interface for local craft 
  (1) D-Type 15 pins interface for External Alarms (dry contacts) 
5.  Slave VCU Cable Connections: 
  (1) RJ-45 interface to Master VCU (Not used in small single-tier deployments) 
  (12) RJ-45 interfaces to VAPs  
  (12) RJ-45 interfaces to Ethernet Switch for LAN service  
  (1) D-Type 9 pins RS-232 interface for local craft