Table 9-6 lists the check items of the signal cable connection. 
Table 9-6
 Checklist for the signal cable connection 
No. 
Item 
The connectors of the signal cables must securely connected. 
The connectors of the signal cables are intact. 
The signal cables are intact. 
The cable ties are evenly spaced. The signal cables are bound neatly with cable 
ties to proper tightness, and arranged at even intervals in the same direction. 
The extra length of the cable ties is cut and removed. The cut surfaces of the 
indoor cables are smooth and have no sharp edges. 
The cable layout facilitates maintenance and expansion. 
Correct and clear labels are attached to both ends of the signal cables. 
 
Table 9-7 lists the checking items for other cable connections. 
Table 9-7
 Checklist for other cable connections 
No. 
Item 
The connectors of the other cables must securely connected. 
Labels on the cables are legible and bound based on the engineering 
requirements. The cables must be bound tightly and neatly. The sheaths of the 
cables must not be damaged. 
Positions for routing the cables must meet requirements of the engineering 
design. 
There are no connectors or joints on each PGND cable. None of PGND cables 
can be short-circuited or reversely connected. In addition, these cables are not 
damaged or broken. 
PGND cables are separately bound from other cables. 
The protection grounding of the pRRU and the surge protection grounding of 
the building share one group of ground conductors. 
 
9.6 Powering on the pRRU 
This section describes the power-on check on the pRRU after the pRRU hardware is installed 