9 Installing a pRRU3907 or pRRU3916
Issue 08 (2016-05-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
205
Table 9-6 lists the check items of the signal cable connection.
Table 9-6
Checklist for the signal cable connection
No.
Item
1
The connectors of the signal cables must securely connected.
2
The connectors of the signal cables are intact.
3
The signal cables are intact.
4
The cable ties are evenly spaced. The signal cables are bound neatly with cable
ties to proper tightness, and arranged at even intervals in the same direction.
ties to proper tightness, and arranged at even intervals in the same direction.
5
The extra length of the cable ties is cut and removed. The cut surfaces of the
indoor cables are smooth and have no sharp edges.
indoor cables are smooth and have no sharp edges.
6
The cable layout facilitates maintenance and expansion.
7
Correct and clear labels are attached to both ends of the signal cables.
Table 9-7 lists the checking items for other cable connections.
Table 9-7
Checklist for other cable connections
No.
Item
1
The connectors of the other cables must securely connected.
2
Labels on the cables are legible and bound based on the engineering
requirements. The cables must be bound tightly and neatly. The sheaths of the
cables must not be damaged.
requirements. The cables must be bound tightly and neatly. The sheaths of the
cables must not be damaged.
3
Positions for routing the cables must meet requirements of the engineering
design.
design.
4
There are no connectors or joints on each PGND cable. None of PGND cables
can be short-circuited or reversely connected. In addition, these cables are not
damaged or broken.
can be short-circuited or reversely connected. In addition, these cables are not
damaged or broken.
5
PGND cables are separately bound from other cables.
6
The protection grounding of the pRRU and the surge protection grounding of
the building share one group of ground conductors.
the building share one group of ground conductors.
9.6 Powering on the pRRU
This section describes the power-on check on the pRRU after the pRRU hardware is installed
and checked.
and checked.