Tait International Limited TBCB1E 用户手册

下载
页码 26
TB9300 Installation and Operation Manual
Installation
61
© Tait Limited July 2012
5
Installation
This chapter provides information on the site requirements for your 
TB9300 equipment and also describes how to install the base station in a 
standard 19 inch rack or cabinet.
If this is your first time installing a TB9300 base station, we recommend 
that you read the entire chapter before beginning the actual installation.
5.1
Before You Begin
5.1.1
Equipment Security
The security of your base station equipment is a high priority. If the site is 
not fully secure, the base station should at least be locked in a secure 
cabinet to prevent unauthorized access.
5.1.2
Grounding and Lightning Protection
Electrical Ground
The base station modules are grounded by physical contact between the 
module case and the subrack. To ensure a good ground connection you 
must tighten each module retaining clamp securely (refer to 
“Final
Reassembly” on page 102
 for the correct torque).
A threaded grounding connector is provided on the rear of the subrack for 
connection to the site ground point (refer to 
“Connecting Up the Base 
Station” on page 79
 for more details).
Lightning Ground
It is extremely important for the security of the site and its equipment that 
you take adequate precautions against lightning strike. Because it is outside 
the scope of this manual to provide comprehensive information on this 
subject, we recommend that you conform to your country’s standards 
organization or regulatory body.