HP Performance Optimized Data Center (POD) 20cp 快速安装指南
Appendix A: HP site assessment 26
Appendix A: HP site assessment
HP POD 20c site assessment checklist
During a survey of the readiness of a proposed customer site for the HP POD 20c, the site is inspected for the
following:
•
Accessibility of machinery for the transportation and installation of the HP POD 20c
•
Assessment of the suitability of the site infrastructure for installing the HP POD 20c and for supporting
infrastructure preparation and serviceability requirements
infrastructure preparation and serviceability requirements
HP responsibilities
Item
Description
Yes No N/A Initial
1. Engagement plan Develop an engagement plan with specific requirements
relating to the proposed installation site.
2. Site visits
Schedule site visits on mutually acceptable dates, during
normal HP business hours.
normal HP business hours.
3. Test equipment
Document any test equipment used in the customer report.
4. Installation site
review
Review and discuss the proposed installation site with the
customer. This initial review includes physical examination of
the proposed installation site and, at the sole discretion of
HP, can include physical measurements of the area size and
the proposed installation site and, at the sole discretion of
HP, can include physical measurements of the area size and
clearances.
5. Indoor/outdoor
installation
Identify whether the HP POD 20c installation is indoors or
outdoors as this can affect the degree and type of
outdoors as this can affect the degree and type of
infrastructure required and the mounting needs.
6. Site pad
•
Inspect the proposed installation site to assess
compliance with the HP POD 20c mounting
specifications. Ensure that the customer is fully aware of
compliance with the HP POD 20c mounting
specifications. Ensure that the customer is fully aware of
the following requirements:
•
Proper support capabilities must exist. If the customer
intends to edge or point load on the utility and cargo
ends, there must be support in the center to prevent
ends, there must be support in the center to prevent
deflection.
•
Upon installation, the POD structure must be leveled to ≤
0.5º, which can be checked at that time with a surveyor’s
transit.
transit.
•
Shimming is allowed around the perimeter of the POD.
•
Place shims in increments across the length of the HP
POD 20c to ensure that the HP POD 20c is level. If
significant shimming is required, shims should be spaced
no less than 1.2 m (4 ft) apart to ensure sufficient load
significant shimming is required, shims should be spaced
no less than 1.2 m (4 ft) apart to ensure sufficient load
transfer.
7. Materials and
construction
inspection
inspection
Visually inspect the materials and construction at the
proposed installation site to identify issues that can impact
proposed installation site to identify issues that can impact
the HP POD 20c installation. Verify that the area is adequate
for truck delivery, staging, and crane location.
for truck delivery, staging, and crane location.