HP Performance Optimized Data Center (POD) 20cp Guida All'Installazione Rapida

Pagina di 38
 
Appendix A: HP site assessment  26 
Appendix A: HP site assessment 
HP POD 20c site assessment checklist 
During a survey of the readiness of a proposed customer site for the HP POD 20c, the site is inspected for the 
following: 
• 
Accessibility of machinery for the transportation and installation of the HP POD 20c 
• 
Assessment of the suitability of the site infrastructure for installing the HP POD 20c and for supporting 
infrastructure preparation and serviceability requirements 
HP responsibilities 
   
Item 
Description 
Yes  No  N/A  Initial 
1. Engagement plan  Develop an engagement plan with specific requirements 
relating to the proposed installation site. 
 
 
 
 
2. Site visits 
Schedule site visits on mutually acceptable dates, during 
normal HP business hours. 
 
 
 
 
3. Test equipment 
Document any test equipment used in the customer report. 
 
 
 
 
4. Installation site 
review 
Review and discuss the proposed installation site with the 
customer. This initial review includes physical examination of 
the proposed installation site and, at the sole discretion of 
HP, can include physical measurements of the area size and 
clearances. 
 
 
 
 
5. Indoor/outdoor 
installation 
Identify whether the HP POD 20c installation is indoors or 
outdoors as this can affect the degree and type of 
infrastructure required and the mounting needs. 
 
 
 
 
6. Site pad 
 
Inspect the proposed installation site to assess 
compliance with the HP POD 20c mounting 
specifications. Ensure that the customer is fully aware of 
the following requirements: 
 
Proper support capabilities must exist. If the customer 
intends to edge or point load on the utility and cargo 
ends, there must be support in the center to prevent 
deflection. 
 
Upon installation, the POD structure must be leveled to  ≤ 
0.5º, which can be checked at that time with a surveyor’s 
transit. 
 
Shimming is allowed around the perimeter of the POD. 
 
Place shims in increments across the length of the HP 
POD 20c to ensure that the HP POD 20c is level. If 
significant shimming is required, shims should be spaced 
no less than 1.2 m (4 ft) apart to ensure sufficient load 
transfer. 
 
 
 
 
7. Materials and 
construction 
inspection 
 
Visually inspect the materials and construction at the 
proposed installation site to identify issues that can impact 
the HP POD 20c installation. Verify that the area is adequate 
for truck delivery, staging, and crane location.