Installing a Cascaded Paragon System 
 
34
 
 
 
l.  Press S to save the configuration. Press F2 to activate the 
Selection menu and verify that the second‐tier Paragon switch is 
properly configured: Select a channel port for the second‐tier 
path and press Enter, then a channel port for a server attached to 
the second‐tier Paragon switch and press Enter. If you can 
properly access and operate the chosen server, the second‐tier 
Paragon switch is properly installed. 
m.  Repeat steps C through L for all remaining (if any) second‐tier 
Paragon switches attached to the Base Unit. 
n.  Edit the names of any servers directly attached to the Base Unit 
and verify the Base Unitʹs configuration as described in steps 6B 
through 6E of the section Installing a Paragon System with a 
Single Matrix Switch
 (on page 24)
Important: If you rearrange a cascaded system or dismantle one and 
rebuild it differently later, you must recycle power to each switch in 
the new cascade. A soft reset allows each switch to retain all user and 
system profiles, and to auto‐detect the current status of its channel 
ports and user ports. Follow the installation steps in this section to 
install the new cascade, but when you power on each switch (which 
must be done in proper tier order, from upper tier to base tier), press 
FUNC on the unitʹs front panel until ʺClear Database Hit Ent/ESC?ʺ 
appears on the LCD panel. Press the ENT and the ESC buttons 
sequentially to execute a partial reset on the database. Please see the 
ʺReset Unitʺ section in 
Paragon II Front Panel Display and Controls (on 
page 16
) for additional information. 
 
Rules of Powering On a Cascaded System 
When powering on existing stable configurations (that is, if you are NOT 
replacing or adding switches and NOT swapping the order of switches) 
or when you are Power Cycling a cascaded configuration, follow the 
sequence below: 
1.  First power on the third‐tier switches (if a third tier exists). 
2.  Then power on the second‐tier switches. 
3.  Finally power on the Paragon II base tier. 
User stations can be powered on and off at any time as needed. 
For configurations where switches are added, replaced, or swapped (in 
order), follow the sequence below: 
1.  First power on the third‐tier switches (if a third tier exists). 
2.  Then power on the second‐tier switches.