Lucent Technologies Release 7 User Manual

Page of 2657
DEFINITY Enterprise Communications Server Release 7 
Maintenance for R7r  
555-230-126  
Issue 4
June 1999
Maintenance Object Repair Procedures 
9-1557
SW-CTL (Switch Control) 
9
Switch Control Reset Test (#93)
This test is destructive if the Switch Control is on the active SPE.
This test resets the Switch Control and determines if it can successfully go 
through its initialization sequence. The test is destructive if the Switch Control 
circuit is on an active SPE since there is the possibility of losing some control 
Any
FAIL
Messages could not be looped back through the control channel interface. If 
the system is equipped with the Standard Reliability configuration, you will 
probably not be able to make or receive calls involving telephones connected 
to the Processor Port Network. 
1. This failure could be due to either a MSSNET circuit pack hardware failure 
or the loss of system timing signals. If the Switch Control is alarmed, then a 
MSSNET circuit pack failure should be suspected. If the Switch Control is 
not alarmed, then investigate the possibility of the loss of system timing 
signals before attempting to replace the MSSNET circuit pack. See 
“TDM-CLK”. A TDM Bus Clock problem may cause many port circuit pack 
red LEDs to light. If only the MSSNET circuit pack LED is lit, suspect the 
MSSNET circuit pack. If many port circuit pack red LEDs are lit, suspect a 
TDM Bus Clock problem. Test #92 and Test #94 run as part of the test 
sequence for the test switch-control C command (where C represents the 
carrier location of the circuit under test). Both tests will fail if the system 
timing signals are lost. If test #94 passes, then do not suspect the loss of 
timing signals. 
Any
 
(cont’
d.)
FAIL
2. Run the short test sequence several times to make sure that this failure is 
occurring consistently. Then run the long test sequence to reset the Switch 
Control. Sometimes running the long test sequence may clear the problem. 
If the test is still failing, proceed to step 3 or 4.
3. If the system is still able to process calls, replace the MSSNET circuit pack 
during a time that would cause the least service disruption. If the system is 
equipped with the High Reliability or Critical Reliability Configuration this 
can be done immediately since a MSSNET circuit pack on the standby SPE 
can be replaced without affecting service. The procedure for replacing the 
MSSNET circuit pack is described in 
Chapter 5.
4. If calls cannot be made, then replace the MSSNET circuit pack 
immediately. The procedure for replacing the MSSNET circuit pack is 
described in ‘‘Replacing SPE Circuit Packs’’ in Chapter 5.
PASS
The control channel interface between the SPE and the Switch Control is 
working correctly
Table 9-591.
TEST #92 Control Channel Interface Test  — Continued
Error 
Code
Test 
Result
Description/ Recommendation
Continued on next page