DEFINITY Enterprise Communications Server Release 8.2
Upgrades and Additions for R8r  
555-233-115  
Issue 1
April 2000
Adding or Removing Cabinet Hardware 
6-92
Add a Control Carrier (Add Duplication) 
6
Relocate Port Carrier B
Refer to 
 to relocate the 
removed port carrier.
Connect Management Terminal or PC
1. Behind control carrier “A,” disconnect the management terminal or PC 
cable from the “TERM” connector, and reconnect the cable to the “DOT” 
(duplication option terminal) connector.
Reseat DEFINITY LAN Gateway System
1. Reseat the LAN Gateway assembly into its backplane connectors. 
Reseat DEFINITY AUDIX System
1. If a DEFINITY AUDIX System resides in the PPN or an EPN (where PPN 
port carrier “B” was relocated), reseat the AUDIX assembly to its 
backplane connectors.
Power Up System
1. At an EPN (where PPN port carrier “B” was relocated), set the main circuit 
breaker to ON.
2. At the PPN, set the main circuit breaker to ON.
3. The system performs a level 4 rebooting process, loading the system 
program and default or current translations from the disk. Rebooting takes 
5 to 11 minutes.
NOTE:
Ignore alarms for now.
4. Type the reset system 4 and press 
Enter 
to copy the translations from 
removable media to memory.
5. Clear any alarms.
6. Type save translation [both] and press 
Enter 
if translation changes were 
made in Step 8.
7. Type restore disk [both] full and press 
Enter 
to copy the translations from 
removable media to disk.
8. Verify that the EMERGENCY TRANSFER CONTROL switch is set to AUTO. 
This restores the system to the normal operating mode.