Issue 1
April 2000
Adding or Removing Cabinet Hardware 
6-94
Add a Switch Node Carrier (Standard Reliability) 
6
Add a Switch Node Carrier (Standard 
Reliability)
To upgrade to a standard reliability R8r with Center Stage Switch (CSS), a switch 
node carrier is added either to an empty “E” carrier position of an existing 
multicarrier port network or to the “D” carrier position.
NOTE:
To avoid moving a port carrier, the preferred practice is to place the new 
switch node carrier in an empty carrier position.
Service Interruption
1. Since the addition of the switch node carrier requires a service 
interruption, notify the customer in advance as to when the addition will 
take place.
Verify System Status
1. Before proceeding, examine the system for alarms and correct all 
problems. The system must be alarm-free.
Disable Alarm Origination
1. Type change system-parameters maintenance and press 
Enter
.
2. Make a note of the 
Alarm Origination Activated
 field 
administration. If the feature is enabled, type n in this field to disable 
Alarm Origination. 
!
WARNING:
If you do not disable Alarm Origination before making changes to the 
switch, the switch may generate alarms, resulting in unnecessary 
trouble tickets. Reducing redundant and unnecessary trouble 
tickets.
NOTE:
For some releases of the software, disable 
Cleared Alarm 
Notification
 and 
Restart Notification
 fields before 
submitting the form.