VACUUM CHECK 
 
A  sufficient  level  of  vacuum  is  necessary  for 
proper  performance  of  the  vacuum  interrupters. 
Although  vacuum  leaks  are  rare,  the  vacuum 
integrity  should  be  checked  periodically.    The 
relationship  between  dielectric  breakdown 
voltage of the contact gap and internal vacuum 
interrupter  pressure  has  been  found  to  be 
generally  predictable.  Therefore,  vacuum 
interrupter  integrity  is  checked  by  performing  a 
high  potential  test  across  the  open  gap  of  the 
interrupter. 
 
TEST EQUIPMENT: 
 
Toshiba offers a compact vacuum checker (Type 
CI35-1D, Figure 11) which enables a quick and 
easy  check  on  vacuum  interrupter  internal 
pressure.  Alternatively,  any  commercially 
available  AC  high  potential  tester  may  be  used 
which  is  capable  of  delivering  at  least  25  milli-
amperes at 10 kV for a period of one minute. 
 
PRECAUTIONS: 
 
Applying  abnormally  high  voltage  across  a  pair 
of contacts in vacuum may produce X-rays. The 
radiation  may  increase  with  the  increase  in 
voltage  and/or  decrease  in  contact  spacing.  X-
radiation  produced  during  this  test  with 
recommended  voltage  and  normal  contact 
spacing  is  extremely  low  and  well  below  the 
maximum  permitted  by  standards.    As  an 
additional  safety  measure,  however,  it  is 
recommended that all personnel keep at least 1 
meter  (3.3  ft)  away  from  the  vacuum  circuit 
breaker while this test is performed. 
 
Radiation exposure hazard. 
X-rays may cause illness or 
injury.  Stay at least 1 meter 
(3.3 ft) away from the circuit 
breaker during the vacuum 
check test. 
 
 
 
Hazardous voltages are 
present during dielectric 
testing which can result in 
severe injury or death.  
Only qualified personnel 
should conduct this testing. 
 
TEST PROCEDURE: 
 
1.   The  contactor  should  be  disconnected  from 
the main circuit and be in the OFF position. 
 
2.   Connect  all  the  line  side  primary  terminals 
together  and  to  the  output  of  the  vacuum 
checker  or  AC  hi-pot  machine.    Connect  all 
the load side primary terminals together and 
to  the  ground  terminal  of  the  vacuum 
checker or AC hi-pot machine. 
 
3.   Increase the voltage from zero to 10kV AC at 
a  rate  of  approximately  1kV  per  second.  
Hold  the  voltage  at  this  value  for  1  minute 
and  observe  the  current  drawn  by  the 
interrupter.  See Figure 12.
 
 
4.   Decrease the voltage back to zero.
 
 
 
Figure 11 - Toshiba Portable Vacuum 
Checker 