Honeywell herculine 2000 User Manual

Page of 128
Installation 
Electrical Installation 
22 
  HercuLine™ 2000 Series Actuator - Installation, Operation and Maintenance Manual 
Revision 7 
  
 7/08 
Step 
Action 
• 
AC power connection 
• 
Auxiliary switches connection 
• 
Relay contact connection 
Relays 3 and 4
Relays 1 and 2
Aux switches 
1 and 2
(SW3 and SW4)
Aux switches 3 
and 4
(SW5 and SW6)
AC power 
connection
 
Figure 12 CE Wiring part 2 
Install new gasket and top cover. Secure top cover with 6 captive screws. 
10 
Reapply AC power to the actuator. 
11 
Actuator is ready for use. 
Input Signal Connections 
 
 
ATTENTION 
Shielded and grounded cables are recommended. 
 
0/4-20 mA Input Signals 
For current signal input, ensure jumper W2 on the CPU PWA is in the “Current” position.  See Figure 27 on 
page 68. Observing polarity, connect the signal input wires TB3–4(+) and TB3–5(-) on CPU terminal board. 
0/1-5 Vdc and 0 to 10 Vdc Input Signals 
For voltage signal input, ensure jumper W2 on the CPU PWA is in the “Voltage” position. See Figure 27 on 
page 68.  Observing polarity, connect the signal input wires to terminals TB3–4(+) and TB3–5(-) of the terminal 
block.