Power Connections 
Depending on which power supply selection is ordered for your actuator, wire the power input (MAINS 
POWER) as described in the previous tables and figures.  Wiring must conform to national and local electrical 
codes. 
CE Wiring 
When wiring the actuator power input for CE approved units, you must also install a MOV and ferrite beads 
supplied with the CE unit.  
You need the following tools: 
• 
5mm hex key 
• 
small flat blade screwdriver 
• 
small needle nose pliers 
 
 
While the unit is powered, a potentially lethal shock hazard exists inside the case. 
Do not open the case while the unit is powered. Do not access the terminals while 
the unit is powered. 
 
Step 
Action 
Remove AC power to actuator. 
Loosen the 6 captive screws (use 5mm hex key) and remove the cover. 
Locate the terminals TB1-1, TB1-2 and ground screw. 
Loosen the screws at terminals TB1-1 and TB1-2. Remove screw used for ground. 
Install the appropriate MOV assembly as shown in Figure 11. 
All ferrites require 1 loop of wire per ferrite. Connect as shown in following steps. 
• 
Current input and output (slidewire emulation) connection 
• 
Communications and digital input connection  
TB1-2
TB1-1
Ground 
screw
Communications 
and digital input
Current input 
and output 
(slidewire 
emulation)
Figure 11  CE wiring part 1