Install system water piping 
(space heating)
 
(continued)
Figure 13 
Circulator zoning plus optional water 
heater piping
Zoning with circulators
1.  Connect  boiler  to  system  as  shown  in  Figure 1
when circulator zoning. The boiler circulator can-
not be used for a zone. It must supply only the boiler
loop.
2.  Install a separate circulator for each zone.
.  Connect  water  heater  (domestic  hot  water)  pip-
ing  to  indirect  storage  water  heater  as  shown  in
Section A of this manual.
 The
PhD Control Module turns off
space heating during water heater heat-
ing.  The  boiler  circulator  will  turn  off,
preventing hot water from circulating to
the system. The flow/check valve shown
on the boiler outlet piping prevents grav-
ity circulation in the boiler loop during
water heater heating.
NOTE 1:
 To  ensure  adequate  flow  rate  through  the
boiler, use the following pipe size on all boiler
loop piping (connecting boiler to and from
the  primary/secondary  connection,  item
21):
-80 or
-10 – 1” or larger.
-1 or
-20 – 1¼” or larger.
-10 – 1½” or larger.
Legend 
Figure
 
13
 boiler
2  PLUS-Line indirect water heater
3  Boiler relief valve (see boiler manual for piping details)
4  Boiler relief valve discharge piping (see boiler manual for 
details)
5  Water heater circulator (see page 7 for suggested sizing)
6  Isolation valves
7  System circulator
8  Diaphragm (or bladder) type expansion tank (see page 3 
for piping of closed-type expansion tank, if used)
9  Air separator [with automatic air vent only on systems using 
diaphragm (or bladder) type expansion tank]
10  Flow/check valves (with weighted seats to prevent gravity 
circulation)
11  Purge/drain valves
12  Boiler circulator
14  Zone circulators, typical
20  Make-up water supply
21  Primary/secondary connection
 Use  at  least  the  minimum  piping  size
above and pipe the boiler using only pri-
mary/secondary piping as shown. Failure
to follow these guidelines could result in
system problems.
B1
Gas