 CAUTION 
ALL PIPE JOINTS AND CONNECTIONS MUST BE TESTED THOROUGHLY FOR GAS LEAKS. USE ONLY 
SOAPY WATER FOR TESTING ON ALL GASES. NEVER USE AN OPEN FLAME TO CHECK FOR GAS LEAKS. 
ALL CONNECTIONS MUST BE CHECKED FOR LEAKS AFTER THE APPLIANCE HAS BEEN PUT INTO 
OPERATION. TEST PRESSURE SHOULD NOT EXCEED 14" W.C. 
 
Do the following to connect the gas supply: 
1.  Check that all control knobs on the sectional range are in the OFF position. 
2.  Purge the gas supply line to clean out dust, dirt, or other foreign matter before connecting the line to the sectional 
range. 
3.  The gas connection piping may have been partially installed at the factory. If necessary, attach the gas 
connection of any appliances mounted on a flue riser. 
4.  Locate the pressure regulator(s) packed with the sectional range. Install the pressure regulator, taking care that 
the direction of gas flow corresponds to the arrow on the side of the pressure regulator. 
 CAUTION 
HOLD THE PRESSURE REGULATOR WITH A WRENCH WHEN TIGHTENING THE CONNECTION TO THE 
SUPPLY PIPE TO AVOID DAMAGE TO THE REGULATOR, VALVE, AND OTHER COMPONENTS. 
 
5.  Install a service shut-off valve to the pressure regulator, and connect the gas supply line to the shut-off valve. 
6.  If applicable, install the vent line of the pressure regulator to the outdoors. 
7.  Turn on the gas and immediately check for leaks using soapy water. 
8.  If the optional sloped enclosure for a flue-mounted model was ordered, install it at this time. 
S
TEP 
8:
 
C
ONNECT 
W
ATER 
S
UPPLY
 
If a rail-mounted fill-hose was ordered (as a special option), there will be a corresponding water connection on the 
back of the section. Connect the water supply. 
S
TEP 
9:
 
C
HECK THE 
I
NSTALLATION
 
Check the installation, as follows: 
1.  Check that all screws and bolts are tightened. 
2.  Check electrical connection(s). 
3.  Check that the gas connection has been made correctly. 
4.  Check water connection(s). 
5.  Move the battery into the final position at which it will be operated. 
6.  Check that the battery is level. If not, adjust the legs or casters. 
7.  Check that the appropriate minimum clearances are satisfied (see page 4)
8.  Check that there is sufficient clearance to open all doors and pull-out all grease trays and crumb trays. 
9.  Check that adequate ventilation (fresh air supply and hood exhaust) is available to the room in which the 
appliance will operate. 
10.  Wipe clean all cooking surfaces (especially griddles). 
11.  Check that nothing is obstructing the air intake openings and/or the combustion-exhaust openings. 
S
TEP 
10:
 
C
HECK 
O
PERATION OF 
E
ACH 
S
ECTION
 
Check the operation of each section, as follows: 
1.  Turn electricity supply on. 
2.  Turn gas supply on. Immediately check all gas connections for leaks using soapy water. 
3.  Turn water supply on (if applicable). Check for water leaks.