Fusion Wideband Installation Procedures
7-30
InterReach Fusion Wideband Installation, Operation, and Reference Manual
CONFIDENTIAL
D-620616-0-20 Rev D
If the 
UL STATUS
 and 
E-HUB STATUS
 LEDs do not turn green/green, check the 
Main Hub LEDs. Refer to page 7-24, item 2 in Table 7-5.
If the fiber jumper is color-coded (for example, “blue” or “red”):
1.
Connect “red” to 
DOWNLINK
 on Expansion Hub.
The 
DL STATUS
 LED should turn green as soon as you connect the fiber. If it does 
not, there is a downlink problem. Make sure you are connecting the correct cable 
to the port.
2.
Connect “blue” to 
UPLINK
 on Expansion Hub.
The 
UL STATUS
 LED turns green on the first Main Hub communication. It may 
take up to 20 seconds to establish communication.
The Expansion Hub’s 
E-HUB STATUS
 LED turns green when the Main Hub sends 
it the frequency band command.
If the 
UL STATUS
 and 
E-HUB STATUS
 LEDs do not turn green/green, check the 
Connecting the 75 Ohm CATV Cables
Considerations:
• Verify that the cable has been tested and the test results are recorded. This informa-
tion is required for the As-Built Document. 
• Verify that only captive centerpin F connectors are used on the solid copper center 
conductor CATV cable from CommScope (or equivalent).
• Verify that the CATV cable is labeled with:
• Fusion Wideband Expansion Hub port number being used
• RAU identifier
• Carrier (for multiple operator systems)
To connect the CATV cables:
1.
Connect the CATV cables to the F ports according to the labels on the cables.
The 
STATUS
 LEDs should be off because the RAUs are not connected at the other 
end of the CATV cable.
2.
Record which cable you are connecting to which port (that is, from the label on 
the cable).
This information is required for the As-Built Document.
3.
Tie-off the cables or use the optional cable manager to avoid damaging the con-
nectors because of cable strain.