Fusion Wideband Installation Procedures
All LEDs blink through the power up sequence. At each port where an RAU is 
detected (drawing current), the port LEDs lights green. The Fusion Wideband 
STATUS
 LED is orange during system boot and should turn green after about 90 
seconds if it finds no faults. This state indicates the band’s are not programmed 
and provides feedback on the status of the RAU connections.
The LEDs blink for 20 seconds as a visual check that they are functioning.
5.
Connect the cross-over Ethernet cable to the PC/laptop and then to the 
RJ-45 
100-BASE-T 
port on the Hub’s front panel.
Programming the Main Hub Using AdminBrowser
• Connect the provided TCP/IP crossover cable to the laptop and then to the 
Admin/LAN 
RJ-45
 port on the Fusion Wideband Main Hub’s front panel.
• Turn on the laptop and start the Fusion Wideband Main Hub.
Windows 2000
1.
Right-click 
My Network Places
 and select 
Properties
.
2.
Highlight 
Internet Protocol (TCP/IP)
 and click 
Properties
. A window similar to 
Figure 7-21
Internet Protocol (TCP/IP) Properties Window