INSTALLATION PROCEDURES
This section provides procedures for installing the Network Listen antenna; connecting the
grounding, base station antenna, IP backhaul, and AC power cables; and installing the shields.
Installation of the microBTS may proceed separately from the installation of the corresponding
BSC. When the installation of the microBTS is completed, refer to the appropriate manuals (see
Related Publications section) for the system turn-up and test procedures. 
6.1
Installation Overview
Installation of the microBTS consists of the following basic steps: 
1. Connecting a grounding cable to the microBTS grounding point.
2. Installing the Network Listen antenna. 
3. Connecting the IP backhaul cable.
4. Connecting the base station antenna coaxial cable to the microBTS antenna port. 
5. Installing the AC power cable and connecting it to the microBTS power port. 
6. Installing the shields. 
6.1.1
Installation Hardware Provided with microBTS Enclosure
The installation hardware that is provided with the microBTS is listed in 
Danger: Wet conditions increase the potential for receiving an electrical shock when installing
or using electrically-powered equipment. To prevent electrical shock, never install or use
electrical equipment in a wet location or during a lightning storm. 
Note: To insure that all connectors and ports remain dust-free during installation,
leave all dust caps and dust protectors in place until directed to remove them. 
Note: If the microBTS will be horizontally mounted, provide drip loops for all cables that
connect to the enclosure. 
Table 4. microBTS Installation Hardware
ITEM
QUANTITY
M8 x 10 hex socket capscrew (for grounding cable)
1
M8 washer (for grounding screw)
1
Grounding cable (1.5 m)
1
AC Power Cable (15 feet)
1
Network Listen antenna
1