SP-3 site preparation protective earth (PE) grounding
checklist
The following items must be completed prior to the installation of the base station site
equipment. Circle the correct letter for the corresponding description items.
Item #
Description
Yes
(Y)
No
(N)
N/A
Comments
1.
Is soil resistivity and site
resistance test on file?
Y
N
N/A
2.
Has connection been
provided to grounding
electrode system?
If yes, circle all that apply:
1. Via a buried ring
ground and driven
rod(s)
2. Via a buried metallic
and electrically
continuous water pipe
3. Via driven ground
rod(s) and/or plate(s)
4. Via electrolytic ground
rod(s)
5. Via grounded building
steel
6. Via grounded grid or
radial
Y
N
N/A
3.
Is lighting mast(s) or air
terminal(s) provided and
bonded?
Y
N
N/A
4.
Is antenna support
structure(s) grounded?
Y
N
N/A
5.
Is antenna tower bonded to
grounding electrode
system?
Y
N
N/A
6.
Are guy wires bonded to
grounding electrode
system?
Y
N
N/A
7.
Are antenna cable shields
grounded at both ends?
Y
N
N/A
Site preparation checklists
SP-3 site preparation protective earth (PE) grounding
checklist
....................................................................................................................................................................................................................................
....................................................................................................................................................................................................................................
B25 RRH4x30
3MN-02023-0001-RJZZA
Issue 0.02
January 2015
Alcatel-Lucent – Proprietary
Use pursuant to applicable agreements