THE CONCRETE PAD 
The standard RS4000 is designed to operate a single leaf gate. Bi-
parting gate systems are possible with the addition of a second 
RS4000 operator. (Consult the factory.) Each RS4000 has its own 
dedicated control board contained within the operator cover. Care 
must be taken to provide separate high voltage and low voltage 
conduits to each operator.  (See Figures 5 and 6.)  Care must also be 
taken in choosing proper placement of the conduit to avoid 
interference with the swinging crank arm which connects to the output 
shaft. See Figure 8A for basic dimensions and guidelines. Figure 10 
illustrates the full sweeping area which the crank arm will encompass 
in a typical gate installation. 
If the optional pedestal kit is used, the Installation of the RS4000 
Mechanical Unit will 
require a suitable concrete 
pad as a mounting base. The 
dimensions of the concrete 
pad should be sufficient to 
allow at least 5" of 
clearance from each edge of 
the pad to the nearest 
pedestal mounting hole. The 
top of the pad should be at 
least 3" above grade to raise 
the operator above any 
standing water. The depth of 
the pad below grade is 
dependent on the weight and 
size of the gate and the soil 
conditions at the site of the 
installation. ALWAYS 
F O L L O W   L O C A L 
BUILDING CODES.   
If no suitable concrete 
base exists, a pad must be 
poured. See Figure
z
6 for 
plans for this pad. If the 
location of the operator is 
such that vehicles have 
the potential of hitting the 
operator, consideration 
should be given to 
installation of protective 
posts in front of the operator. 
If a suitable concrete base already exists 
for mounting the operator it will be 
necessary to drill mounting holes for the 
RS4000 operator.  3/4" mounting holes are 
located on the front and rear of the optional 
pedestal. The bolt pattern is shown in 
Figure
z
6. The mounting bolts should be 
1/2" diameter or larger.  "Red head"  or 
wedge anchor concrete bolts are usually 
satisfactory.   
If mounting anchor bolts are to be installed prior to 
pouring the pad, pay particular attention to the bolt 
pattern and the location of the mounting holes with 
respect to the center line of the gate hinge. It is critical for 
the proper operation of the Arm that the center line of the 
output shaft of the RS4000 operator be located exactly as 
shown on the bolt pattern drawing, Figure 6.  
 
ALTERNATE 4 X 4 POST MOUNT
 
The RS4000 operator offers an alternative to the optional pedestal kit 
for mounting installation. A standard architectural 4 x 4 x 1/8 wall 
steel tube may be substituted for the pedestal and installed in a similar 
manner to a fence post:  Dig a hole of proper diameter (approximately 
12”) and suitable depth per local codes, and set the 4
Z
x
Z
4 post in 
concrete. Make sure the post is plumb and level. The top of the post 
should be cut off clean and square and should extend at least 18” 
B:
 PREPARING THE SITE 
Figure 5:  Pad Configuration 
106505 
Figure 6:  Operator Footprint 
106506