Avaya 03-300430 User Manual

Page of 2574
Communication Manager Maintenance-Object Repair Procedures
2308 Maintenance Procedures for Avaya Communication Manager 3.0, Media Gateways and Servers
 
NPE Crosstalk Test (#6)
The NPE Crosstalk test verifies that a port’s NPE channel talks on the time slot assigned to it 
and does not cross over to time slots reserved for other connections. If the NPE is not working 
correctly, 1-way and noisy connections may be observed. The test takes 20 to 30 seconds to 
complete.
Port Audit and Update test (#36)
X
X
ND
Transmission test - ATMS (#844-848)
2
ND
1. D = Destructive, ND = Nondestructive
2. ATMS tests are not part of either sequence. They are run either on demand with test 
analog-testcall, or by the ATMS schedule.
Order of Investigation
Short Test
Sequence
Long Test
Sequence
D/ND
1
 2 of 2
Table 829: Test #6 NPE Crosstalk Test 
Error
Code
Test
Result
Description / Recommendation
ABRT
Could not allocate the necessary system resources to run this test.
1. Retry the command at 1-minute intervals up to 5 times.
1000
ABRT
System resources required to run this test are not available. The trunk 
may be busy with a valid call. Use display trunk-group xx to 
determine the trunk group/member number of the port. Use status 
trunk
 to determine the service state of the port. If the service state 
indicates that the port is in use, then the port is unavailable for certain 
tests. Wait until the port is idle before retesting.
1. If the port status is active, but the port is idle (no connected ports), 
then check the Error Log for Error Type 1025 (see Error Log table for 
description of this error and required actions). The port may be 
locked up.
2. If the port status is idle, then retry the command at 1-minute intervals 
up to 5 times.
1001
ABRT
System resources required to run this test are not available. This could 
be due to a failure to seize the port.
1. Retry the command at 1-minute intervals up to 5 times.
 1 of 3