SPID Facility Test
This test is used to verify the wiring and operation of the signaling link between the switch and a 
endpoint or adjunct on a BRI interface.  This test is not executed from the administration 
terminal, but rather is executed by using a BRI test set equipped with a display.  The test set 
may replace the BRI set, ASAI or Avaya adjunct under test by plugging it into the same jack or 
by bridging it onto the wiring at some point between the switch and the endpoint (or adjunct), 
thereby creating a pseudo-BRI multipoint configuration.
When plugged into the port in this manner, the test set establishes a signaling link connection 
with the switch and attempts to complete Service Profile IDentifier (SPID) initialization by using 
the Service SPID administered for the system (see the System Maintenance Administration 
screen).  If the test set displays the correct administered port address for the endpoint or 
adjunct under test, the test passes (see 
on page 734).  If after 
one minute nothing is displayed on the test set, the test fails.
Table 248: SPID Facility Test 
Test 
Result
Description / Recommendation
FAIL
No response is received from the endpoint.
1. Check the physical wiring between the switch and the endpoint or adjunct.
2. If test continues to fail, escalate to the next tier.
FAIL
Display does not match administered port address for the endpoint or adjunct.
1. Change station administration for endpoint or adjunct to match displayed port 
address.
2. If test continues to fail, escalate the problem.