• Wrist strap or other personal grounding device to prevent electro-static discharge (ESD)
occurrences.
• Antistatic mat or antistatic foam to set the PPM on.
• Small flat-blade screwdriver for removing the CFP module socket cover.
• Fiber-optic end-face cleaning tools and inspection equipment. For complete information
on inspecting and cleaning fiber-optic connections, see the
document.
Tools/Equipment
"NTP-G179 Install the TXP, MXP, AR_MXP, AR_XP, 100G-LC-C, 10x10G-LC, CFP-LC,
ADM-10G, and OTU2_XP Cards" task in the chapter "Provision Transponder and Muxponder
Cards" of Cisco ONS 15454 DWDM Configuration Guide
Prerequisite Procedures
As needed
Required/As Needed
Onsite
Onsite/Remote
Provisioning or higher
Security Level
Procedure
Step 1
Install PPMs. Complete the necessary task as applicable:
Step 2
Provision the PPM. Complete the necessary task as applicable:
Step 3
Delete the PPM. Complete the necessary task as applicable:
Stop. You have completed this procedure.
DLP-G723 Install PPM on a Line Card
This task installs PPM on a line card. The PPMs provide a fiber interface to the card.
Purpose